BEING SENT ON BEHALF OF SCHNEIDER ELECTRIC
******************************************************************************
Attention All:
This email serves as a notification
to request permission to perform work in which our subcontractors Davis Houk
Mechanical and Alpha will be performing demolition, installing new
ductwork/piping in the area of 1st floor of Roger Adams Laboratory North
(please see attached drawing mark-ups), and installing new BAS controls.
Schneider Electric is requesting this work to be performed beginning January 6th,
2020 through March 13th, 2020. Attached you will find a drawing
markup showing the time frames in which this work is schedule to be done. Also
attached you will find a detailed description of the work that will be
performed. This area of the building that may possibly be affected by noise
associated with work including new ductwork installation, ductwork demolition,
and ceiling removal. Subsequent outage request for this scope of work will be
sent out to Josh Whitson for official review and approval.
Davis Houk Mechanical will start on
Monday, January 6th with the removal of the ceiling tile in Corridor
C100A and continue on into Rm. 101 on and start the removal of the ceiling tile
in office/lab spaces. The work on the floor will be split up into two
separate timelines. Work performed in Rooms 101 – 109 will begin January 6th
and last until February 12th. Work in Rooms 189 – 195 will begin on
February 13th and last through March 13th. The
estimated duration of the construction will be approximately 10 weeks. The
start times of the subcontractor will be at 6 am and will go through 4 pm
Monday-Friday. SE will track the progress of the of the project daily and
communicate with the University, i.e. Karla Southern, and Chad Dennis. These
dates are tentative and subject to change based on our ability to gain clear
access to the rooms during the time periods that are being requested.
The following is a description of the work that will be
done:
- The removal of ceiling tile along corridor C100A and
Rm. 101 – 109 and 189 - 195
- Installation of new ductwork in Rm. 101, 101, 101B,
101C, 101D, 103, 105, 107, 108, 109, C100A, 189, 191, 193, 195 and
corridor C100A.
- Removal of ductwork in corridor C100A and Rm. 101 – 109
and 189 – 195.
- Installation of new BAS controls and rough in of
conduit in corridor C100A and Rm. 101 – 109 and 189 – 195.
If there are any additional questions regarding the
construction work associated with the work on the 1st floor in Roger
Adams Laboratory North feel free to contact me.
Iman S. Hoggard
Site Project Manager Energy & Sustainability Services Schneider Electric |
1650 West Crosby Rd
Carrollton, TX 75006 United States |