ESCO Project # 5 Meeting Notes: 2/5/19

Esco Project #5 Meeting:  2/5/19



Window replacement schedule in PENDING status

Schneider will be notifying Danielle Cruzan of any spaces they need to enter for measurements PRIOR to entering the rooms so she can get permission from the faculty member/GSO.

Will need any info on special events, outages, etc. that will be happening in the buildings to ensure there are no noise disruptions during these times.


ESCO Meeting Notes: 1/29/19

ESCO Project #5 Meeting - 1/29/19




467 NL Status Update:  Josh with F & S checked and it was still sealed off as the contractors prepped the room.


Safety Vests & Badges:  All Schneider Electric contractors will be wearing safety vests and badges to identify themselves as they move through the buildings.