Tuesday, June 25, 2019

VENTILATION OUTAGE - RAL 197, 199, 295 - JUNE 24 - 5AM TO 5PM


TO ALL IN RAL 197, 199, & 295:

As part of the CAMPUS Heat Recovery Project, there will be a VENTILATION OUTAGE in your spaces on Monday, June 24 from 5am to 5pm.  This means there will be NO EXHAUST FANS so using the hoods is HIGHLY discouraged during this outage.  This outage is being conducted to relocate conduit for the exhaust fans in support of the Heat Recovery Project.  Further details of the outage are below:

Facilities and Services is requesting an outage on
VENTILATION at ROGER ADAMS LABORATORY (0116) from 2019/06/24 05:00 to 2019/06/24 17:00 -
Ventilation Fan No. : ALL FANS ASSOCIATED WITH HD-16
Ventilation Area. : ROOMS 197, 199, 295
Outage ID : 20725
Outage Reason : TEMPORARY RELOCATION OF CONDUIT FOR EXHAUST FANS IN SUPPORT OF PROJECT U16061
Building Sections affected : ROOMS 197, 199, 295
Building Services affected : ALL FANS ASSOCIATED WITH HD-16(ROOMS 197, 199, 295-1 HOOD IN EACH ROOM)
This information will be posted on the SCS ESCO blog:  www.scsesco.blogspot.com.   If you have any further questions, please let us know ASAP.


Thanks,

D. Chad Stevens, MPA
Director of Facilities and Safety
School of Chemical Sciences
University of Illinois - Urbana-Champaign

168 Noyes Lab, MC-712
505 S. Mathews Avenue
Urbana, Illinois 61801
phone:  217.333.6365
cell:  217.493.7927

https://scs.illinois.edu/resources/facilities-management-and-safety-resources



VENTILATION OUTAGE - RAL 194, 210A, 294, 304, 112A - FRIDAY, JUNE 21 - 5AM TO 5PM


TO ALL IN RAL 194, 210A, 294, 304, & 112A:

As part of the CAMPUS Heat Recovery Project, there will be a VENTILATION OUTAGE in your spaces on Monday, June 24 from 5am to 5pm.  This means there will be NO EXHAUST FANS so using the hoods is HIGHLY discouraged during this outage.  This outage is being conducted to relocate conduit for the exhaust fans in support of the Heat Recovery Project.  Further details of the outage are below:

VENTILATION at ROGER ADAMS LABORATORY (0116) from 2019/06/21 05:00 to 2019/06/21 17:00 -
Ventilation Fan No. : ALL FANS ASSOCIATED WITH HD-19
Ventilation Area. : ROOMS 194, 210A, 294, 304, 112A
Outage ID : 20723
Outage Reason : PERMANENT RELOCATION OF CONDUIT FOR EXHAUST FANS IN SUPPORT OF PROJECT U16061
Building Sections affected : ROOMS 194, 210A, 294, 304, 112A
Building Services affected : EXHAUST FANS ASSOCIATED WITH HD-19(ROOMS 194, 210A, 294, 304, 112A)
This information will be posted on the SCS ESCO blog:  www.scsesco.blogspot.com.   If you have any further questions, please let us know ASAP.


Thanks,

D. Chad Stevens, MPA
Director of Facilities and Safety
School of Chemical Sciences
University of Illinois - Urbana-Champaign

168 Noyes Lab, MC-712
505 S. Mathews Avenue
Urbana, Illinois 61801
phone:  217.333.6365
cell:  217.493.7927

https://scs.illinois.edu/resources/facilities-management-and-safety-resources





CHILLED WATER OUTAGE - NORTH RAL - JUNE 25, 26, 27 - 5AM TO 5PM DAILY


TO ALL IN NORTH RAL:

As part of the CAMPUS Heat Recovery Project occurring in RAL, there will be a CHILLED WATER SHUTDOWN on Tuesday, June 25, Wednesday, June 26 and Thursday, June 27.   The outage will be from 5:00am to 5:00pm each day.    Those spaces directly affected by the shutdown were informed in a separate email yesterday but they are attached to this email as well.  There is also a questionnaire attached to answer any questions about this shutdown.  Those affected may notice warmer temperatures during the outage.  The reason for this outage to is tie into the chilled water loop for the new chillers that will be installed in North RAL.  Further details of the outage are below:

Facilities and Services is requesting an outage on
CHILLED WATER at ROGER ADAMS LABORATORY (0116) from 2019/06/25 05:00 to 2019/06/27 17:00 -
Associated Project Manager. : JOSH WHITSON
Outage ID : 20726
Outage Reason : SHUTDOWN OF CHILLED WATER SYSTEM IN RAL IN ORDER TO TIE INTO THE CAMPUS CHILLED WATER LOOP. IN SUPPORT OF PROJECT U16061.
Building Sections affected : ALL EQUIP ASSOCIATED WITH TRANE AND MCQUAY CHILLERS. AHU-S25, AHU-S18, AHU-S6, SA-405, TWO FANS IN CEILING OF ROOM 221, AND ONE FAN IN ROOM 19.
Building Services affected : COOLING
Building Occupants Effect : WARMER TEMPS
Comments : null
This information will also be posted on the SCS ESCO blog:  www.scsesco.blogspot.com.  If you have any questions or concerns, please let us know ASAP.

Thanks,

D. Chad Stevens, MPA
Director of Facilities and Safety
School of Chemical Sciences
University of Illinois - Urbana-Champaign

168 Noyes Lab, MC-712
505 S. Mathews Avenue
Urbana, Illinois 61801
phone:  217.333.6365
cell:  217.493.7927

https://scs.illinois.edu/resources/facilities-management-and-safety-resources

Monday, April 1, 2019

RAL South Testing and Balancing - 3 Week Look Ahead


LSOs,

   Attached is the testing and balancing schedule for RAL South for the next three weeks. This testing is part of the preparations for the ESCO project. It is currently estimated that this process will take 30-60 minutes per room. Once the mock-up is done for room 173, I will have a better idea of what this process will entail to better advise you on what interruptions you should expect and what preparations will need to be made. I will be meeting with each of you the week prior to your group’s scheduled testing to discuss your necessary preparations. In the meantime, if you have any questions about this testing, feel free to contact me.

Shane Brownfield
Safety Officer – School of Chemical Sciences
94 Roger Adams Lab
217-300-6618
sbrownfi@illinois.edu






Monday, February 11, 2019

ESCO Project # 5 Meeting Notes: 2/5/19

Esco Project #5 Meeting:  2/5/19



Window replacement schedule in PENDING status

Schneider will be notifying Danielle Cruzan of any spaces they need to enter for measurements PRIOR to entering the rooms so she can get permission from the faculty member/GSO.

Will need any info on special events, outages, etc. that will be happening in the buildings to ensure there are no noise disruptions during these times.


ESCO Meeting Notes: 1/29/19

ESCO Project #5 Meeting - 1/29/19




467 NL Status Update:  Josh with F & S checked and it was still sealed off as the contractors prepped the room.


Safety Vests & Badges:  All Schneider Electric contractors will be wearing safety vests and badges to identify themselves as they move through the buildings.