TO ALL IN RAL NORTH:
The ESCO project crew needs to do further demolition on the
west shaft in RAL North and will be doing this work Dec. 26 and Dec. 27 from
6:00am to 4:00pm both days. Please see further details from Schneider
Electric below:
**************************************************************************************
All,
This email serves as a notification
to request permission to perform demolition in the West shaft in Roger Adams
Laboratory North. An additional duct was discovered in the west shaft during
the abatement process that will need to be removed as discussed in our previous
meeting. The location of the West Shaft is located south of the elevator in
Roger Adams Laboratory North. The demolition would start on the fourth floor
and continue through each floor ending at the ground floor. The existing
partitions and protective measures in the spaces and surrounding areas are
currently still in place and will be utilized for this demolition process. The
entire process will take two days. Please note that the ductwork has already
been abated and passed clearance testing. Disruptions to building occupants
will be kept at a minimum. All measures will be taken to make sure that process
does not affect staff and students.
Davis Houk Mechanical is
requesting for this demolition to begin on December 26th and 27th.
Davis Houk will begin work at 6 am and complete by 4 pm daily. Access to
the elevator may be needed to remove debris and bring in materials.
No outages will be needed for this scope of work. Please note that
no work will be done or scheduled until Schneider Electric receives a notice to
proceed from the University. If you have any additional questions feel
free to contact me.
Kindest Regards,
Iman S. Hoggard
Site Project Manager Energy & Sustainability Services Schneider Electric |