RAL South BAS installation Beginning Next Week


All,

              This email serves as a reminder that Alpha will begin installation of BAS controls in RAL South will be beginning on Monday, October 21st and ending on November 5th. This work will involve running conduit and wiring from the VAV controls in the hallways through the wall and down along the wall adjacent to the doorways as well as installation of a new thermostat. This portion of the project will affect both labs as well as offices/break areas. Each installation is expected to take 30-60 minutes and should be only minimally intrusive as the work will take place in the hallways/closets or just inside the doorway. You may experience some noise from the drilling needed to make holes for the conduit. Below is the proposed schedule for this project as well as necessary preparations:

   October 21st: Sarlah (4th floor) (453,455,457,459), Katzenellenbogen (4th floor) (449,451), Burke (456, 458, 460 only)
   October 22nd: Burke (all remaining areas) (437,439,441,443,444,445,446,447,448,450)
   October 23rd: Moore (472,473,474,475,476,477,478,479), Chan (3rd floor) (336,338)
   October 24th: Zimmerman (340,341,342,343,344,346,347,348,350)
   October 25th: Mitchell (349,351,353,355,360), Sarlah (3rd floor) (356,357,358,359)

   October 28th: Van der Donk (145,147,149,151,153,154,155,156,157,158,159,160)
   October 29th: Denmark (236,337,238,239,240,241,242,243,244,246,248,250)
   October 30th: Hergenrother (233,249,251,252,253,254,255,256,257,258,259,260)
   October 31st: Chan(2nd floor) (272,274,276,278), Sarlah (2nd floor) (273,275,277,279)
   November 1st: Silverman (135A, 140/140B done first) (135,135A,136,137,138,139,140,140B,141,143)

   November 4th: Sweedler (74,75,76,77,78,79), Vura-Weis (45), Shen (49,51,55)
   November 5th: Rodriguez-Lopez (40,42,46,48,50,57,59,60), Han (38,52,56)

Preparations to be made before leaving the day prior:
      -Make sure the bench area closest to the door is clear so there is no risk of chemicals being knocked over or items being broken.

This request was prompted as a result of an inability to complete the work that has been approved on the ground floor of RAL North. We are unable to get into Rm. 5, 12, and 14 until after November 5th. This work in RAL South will supplement RAL North work. Alpha will be doing an average of 10 rooms per day. Alpha will be working during normal business hours between 6 am – 3 pm Monday thru Friday. If there is any additional information needed feel free to contact me.

Kindest Regards,

Iman S. Hoggard
Site Project Manager
Energy & Sustainability Services
Schneider Electric
M  +1 (313) 363 9414
E  iman.hoggard@schneider-electric.com
1650 West Crosby Rd
Carrollton, TX 75006
United States
  

    





No comments:

Post a Comment